Yes.
countCLOUD.pro requires a total count duration to be entered when creating a count. This duration can then be split into multiple start/stop times allowing for peak period counts to be processed on a single day, or multiple counting days to be processed into a single count sheet.
If processing counts over multiple days on a single count be sure the first and last date are within 7 days of each other as the countCLOUD Count Sheet is set up for a maximum of a 7-day count.
The following process shows the steps of setting up two sequential 13-hour counts. This same process can be used for peak period counts or weekday/weekend counts by changing the initial Individual Count Duration and counting periods to fit your specific needs.
- Select the Count Type, Classifications, Individual Count Duration, and Quantity of Counts to Create. Click CREATE.
- The Individual Count Duration should be set to the full duration of processing for the count (26-hours for this example).
-

- Enter the Location Reference and place the approach labels and camera location icon over the aerial image. Click SAVE & CONTINUE
- The count will default to a single counting period with the duration equaling the Individual Count Duration set in Step 1. To add an additional start/stop time click the "+" icon next to the Start date, Start time, and Duration cells.
- Update the Durations in each counting period so that the total sum of the counting durations is equal to or less than the Individual Count Duration entered at the start of the count.
- Enter the Start Date and Time for each counting period.
- Select the video or videos for the counting periods and click SAVE & CONTINUE
- Review the provided information and click SUBMIT FOR PROCESSING if correct. Click BACK and update any information of mistakes are noted.